Summit Fertilizers – Self-performance Concrete Ring Beam

Our Role

Jan 23 – June 23

  • MMS civil crew excavated trenches
  • MMS carpenters installed RMD panels for concrete ring beam
  • Metro Concrete supplied concrete and labor for pouring
  • Steel cages constructed on site by MMS steel fixers.
  • Blinding installed in trenches
  • Cages placed inside formwork by MMS crew
  • Pour day was 40m3 (once a week for 7 weeks)
  • ESO surveyed formwork before pours